Period-end closing in SAP PS makes sure that the costs, revenues and other values of a project are complete before they are passed on to accounting. The exact steps depend on the type of project: a customer project needs results analysis, while an investment project is mainly settled to an asset.

Advertisement

Period-end closing steps and T-codes

The steps build on each other, so their order matters. Settlement comes last, because it passes on the result of the previous steps. Not every project needs every step.

StepPurposeIndividualCollective
1. Overhead calculationAdds indirect costs to the projectCJ44CJ45
2. Progress analysisDetermines the percentage of completion and earned valueCNE1CNE2
3. Results analysisDetermines the revenue, cost of sales, work in process and reservesKKA2KKAJ
4. Generate settlement rulesCreates missing settlement rules, if you use this functionCJB2
5. SettlementPasses costs, revenues and results to the receiversCJ88CJ8G

Depending on your processes, template allocation, interest calculation, cost forecast and incoming orders are carried out before settlement as well. SAP Learning presents the activities of a logistics project.

1. Overhead calculation

Overhead costs, such as administration or indirect labor, are charged to the project with rates defined in a costing sheet.

Example: direct costs of $100,000 and an overhead rate of 10% give an overhead of $10,000. The project is debited, and the cost center that provides the service is credited.

2. Progress analysis

Progress analysis calculates the percentage of completion of the project. It is a separate evaluation, but its result can also be used by results analysis. See progress analysis.

3. Results analysis

Results analysis compares the costs and revenues of a customer project, and determines what should be shown in the accounts at the end of the period: recognized revenue, cost of sales, work in process and reserves. It is controlled by the results analysis key of the WBS element, usually the billing element.

Common approaches are the percentage of completion method, where revenue follows the progress of the costs, and revenue-based methods, where costs follow the billed revenue.

Example with the percentage of completion method

ValueAmount
Planned costs$1,000,000
Planned revenue$1,500,000
Actual costs to date$600,000
Percentage of completion: 600,000 / 1,000,00060%
Revenue to recognize to date: 1,500,000 × 60%$900,000
Already recognized in earlier periods$650,000
Revenue to recognize in this period$250,000

The $900,000 is the cumulative value since the start of the project. Only the difference from the earlier periods, $250,000, belongs to the current period.

Results analysis only calculates and stores the values. In the classic process, they are posted to Financial Accounting and Profitability Analysis by settlement.

Advertisement

4. Settlement

Settlement transfers the costs and revenues of WBS elements and networks to one or more receivers. It depends on:

  • Settlement rule: the receivers, the shares and the settlement type of each object.

  • Settlement profile: the receivers that are allowed.

  • Settlement type: periodic settlement settles the costs of one period, full settlement settles all costs up to that date.

Type of projectTypical receiver
Internal or overhead projectCost center, order or another WBS element
Investment projectAsset under construction, then the final asset
Customer projectProfitability segment

Example

A construction project has two WBS elements:

  • Planning and design: $100,000, settled to the cost center of the planning department.

  • Construction: $500,000, settled to an asset under construction.

After settlement, the balance of both WBS elements is zero, and the costs are shown on their receivers.

Revenue recognition in S/4HANA

Billing a customer and recognizing revenue are two different things. In SAP S/4HANA, depending on the edition, event-based revenue recognition can replace period-end results analysis: the values are posted together with each cost or billing document. See what changed for SAP PS in S/4HANA.

Tips for a smooth period-end closing

  • Check the settlement rules and results analysis keys of new WBS elements before the closing.

  • Make sure that goods receipts, invoices and timesheets are posted first.

  • Start each step as a test run, and read the error log.

  • Schedule collective runs as background jobs, in the order above.

  • Reconcile the project balances with FI and CO after settlement.

Next: Reporting