Budgeting
Updated November 2026
In SAP Project System, budgeting makes it possible to monitor the funds assigned to a project and to prevent budget overruns.
The approved cost structure for executing a project is documented by distributing the budget to the WBS elements of this project. This typically occurs during the approval phase, before the execution phase starts.
Budgets can only be assigned to WBS elements in the PS module. Networks cannot be budgeted, but the costs of the networks and network activities assigned to a WBS element are considered by availability control.
How to check the budget of a WBS element
To display the original budget of a project or WBS element, use transaction CJ31. To compare the budget with actual costs and commitments, run report S_ALR_87013558.
| I want to see… | Use |
|---|---|
| The original budget per WBS element | CJ31 |
| Budget, actual, commitment, remaining plan and assigned values | S_ALR_87013558 |
| Budget, actual and variance | S_ALR_87013557 |
| The released budget | CJ33 |
| The actual cost line items behind the figures | CJI3 |
| The commitment line items (purchase requisitions and orders) | CJI5 |
| The budget in the database | BPGE (overall) and BPJA (annual): see SAP PS tables |
Budgeting functions in SAP PS
Original budget
The original budget of a project is entered with transaction CJ30 and displayed with CJ31. A budget can be defined as an overall budget or distributed by year. This is configured in the budget profile.
Budget updates: supplements, returns and transfers
Budget updates are used to change the project budget without changing the original budget, so that the original budget can still be compared with the current budget.
| Update | T-code | What it does |
|---|---|---|
| Supplement to project | CJ36 | Adds new budget and so increases the total budget of the project |
| Supplement in project | CJ37 | Adds budget to WBS elements as long as distributable budget is still available in the project |
| Return from project | CJ35 | Reduces the total budget of the project |
| Return in project | CJ38 | Returns budget from WBS elements within the project |
| Transfer | CJ34 | Moves budget from one WBS element to another. Transfers between projects are possible |
Budget release
Budget release (CJ32) is an optional additional step that authorizes the budget before it is spent. If you use it, the budget must be released before the project is executed.
Budget carry-forward
Budget carry-forward transfers the budget that was not consumed in a fiscal year to the following fiscal year. This is done with transaction CJCO. Carry forward the open commitments first, with CJCF.
Availability control
Availability control compares the budget with the assigned values, and can warn the user, send a mail or block the posting when a tolerance limit is reached. It is activated with CJBV and deactivated with CJBW.
In simple terms, the assigned value is made up of:
actual costs posted to the WBS element,
commitments, such as purchase requisitions and purchase orders,
for apportioned networks and orders, the higher of their planned costs and their actual costs plus commitments.
Costs planned directly on the WBS element, for example with CJ40, do not consume the budget. Cost planning and budgeting are separate steps.
If a posting is blocked, see how to fix budget exceeded errors, with a worked example.