Progress Analysis

Updated November 2026

Progress analysis in SAP PS measures how much of a project has been completed, and compares it with what was planned and what it has cost. Its two main results are the percentage of completion (POC) and the earned value.

Advertisement

Progress analysis T-codes

T-codePurpose
CNE1Progress determination, individual processing
CNE2Progress determination, collective processing
CNE5Progress analysis report
CNPAWBProgress analysis workbench
COMPXPDProgress tracking for components

How it works

  1. Plan the dates and costs of the project.

  2. Choose a measurement method for each object, or use the defaults from customizing.

  3. Record the progress: confirmations, actual dates, milestones, actual costs or estimates, depending on the method.

  4. Calculate the progress with CNE1 or CNE2. The results are stored in a progress version.

  5. Analyze the results, for example with CNE5.

The progress version is defined in customizing and contains the control data of the calculation. Several versions allow you to compare, for example, two calculation methods.

Measurement techniques

SAP provides the following techniques, described by SAP Learning:

TechniqueHow the POC is determinedSuited to
Start-finish ruleA fixed POC at the start, the rest at the finish, for example 0-100 or 20-80Short tasks
Milestone techniqueEach milestone reached gives a defined POCLonger tasks with clear events
EstimationThe POC is estimated and entered, up to a maximum until the task is finishedWork that is hard to measure
Time proportionalityThe POC follows the durationContinuous work, such as project management
Cost proportionalityThe POC follows the costsObjects whose progress follows their costs
Quantity proportionalityThe POC follows a quantity, through a statistical key figureWork measured in units
Degree of processingThe POC comes from the confirmations (activities and actual POC only)Confirmed network activities
Secondary proportionalityThe POC follows another objectAccompanying work, such as quality control
User-definedCalculated by a customer enhancementSpecial cases

Use the same technique for the planned and the actual POC whenever possible, so that the two can be compared.

Key figures

Key figureMeaningFormula
BCWSBudgeted cost of work scheduled: planned costs according to the planned progressPlanned POC × overall costs
BCWPBudgeted cost of work performed: earned value according to the actual progressActual POC × overall costs
ACWPActual cost of work performedActual costs
SVSchedule varianceBCWP − BCWS
CVCost varianceBCWP − ACWP
CPICost performance indexBCWP / ACWP

The overall costs are the planned costs or the budget, depending on the progress version.

Advertisement

Worked example

A construction project has three phases, weighted by their planned costs:

PhasePlanned costsWeightActual POCEarned value
Foundation300,00030%90%270,000
Structure500,00050%36%180,000
Finishing200,00020%0%0
Project1,000,000100%45%450,000

According to the plan, 50% should have been completed, and the actual costs are 480,000:

  • SV = 450,000 − 500,000 = −50,000: the project is behind schedule. Its progress is 5 percentage points below the plan.

  • CV = 450,000 − 480,000 = −30,000: the work performed has cost more than planned.

  • CPI = 450,000 / 480,000 = 0.94: each unit of cost has produced 0.94 of earned value.

The progress of 45% does not mean that the project is 5% late in time. It compares the value of the work done with the value of the work planned.

Aggregated and non-aggregated values

SAP calculates the progress of each object, and can also aggregate it up the hierarchy with weights. The project cost plan is the recommended weighting factor, as in the example above. An aggregated POC on the billing element can be used by results analysis, see period-end closing.

Tips

  • Set a maximum POC for estimates: 80% is a common value. It avoids tasks that stay "90% done" for months.

  • Choose simple techniques that people will really keep up to date.

  • Update confirmations, dates and milestones before you run the calculation.

  • Do not mix very different techniques within one WBS level if you want to compare the objects.

Next: Period-End Closing