Progress Analysis
Updated November 2026
Progress analysis in SAP PS measures how much of a project has been completed, and compares it with what was planned and what it has cost. Its two main results are the percentage of completion (POC) and the earned value.
Progress analysis T-codes
| T-code | Purpose |
|---|---|
CNE1 | Progress determination, individual processing |
CNE2 | Progress determination, collective processing |
CNE5 | Progress analysis report |
CNPAWB | Progress analysis workbench |
COMPXPD | Progress tracking for components |
How it works
Plan the dates and costs of the project.
Choose a measurement method for each object, or use the defaults from customizing.
Record the progress: confirmations, actual dates, milestones, actual costs or estimates, depending on the method.
Calculate the progress with
CNE1orCNE2. The results are stored in a progress version.Analyze the results, for example with
CNE5.
The progress version is defined in customizing and contains the control data of the calculation. Several versions allow you to compare, for example, two calculation methods.
Measurement techniques
SAP provides the following techniques, described by SAP Learning:
| Technique | How the POC is determined | Suited to |
|---|---|---|
| Start-finish rule | A fixed POC at the start, the rest at the finish, for example 0-100 or 20-80 | Short tasks |
| Milestone technique | Each milestone reached gives a defined POC | Longer tasks with clear events |
| Estimation | The POC is estimated and entered, up to a maximum until the task is finished | Work that is hard to measure |
| Time proportionality | The POC follows the duration | Continuous work, such as project management |
| Cost proportionality | The POC follows the costs | Objects whose progress follows their costs |
| Quantity proportionality | The POC follows a quantity, through a statistical key figure | Work measured in units |
| Degree of processing | The POC comes from the confirmations (activities and actual POC only) | Confirmed network activities |
| Secondary proportionality | The POC follows another object | Accompanying work, such as quality control |
| User-defined | Calculated by a customer enhancement | Special cases |
Use the same technique for the planned and the actual POC whenever possible, so that the two can be compared.
Key figures
| Key figure | Meaning | Formula |
|---|---|---|
| BCWS | Budgeted cost of work scheduled: planned costs according to the planned progress | Planned POC × overall costs |
| BCWP | Budgeted cost of work performed: earned value according to the actual progress | Actual POC × overall costs |
| ACWP | Actual cost of work performed | Actual costs |
| SV | Schedule variance | BCWP − BCWS |
| CV | Cost variance | BCWP − ACWP |
| CPI | Cost performance index | BCWP / ACWP |
The overall costs are the planned costs or the budget, depending on the progress version.
Worked example
A construction project has three phases, weighted by their planned costs:
| Phase | Planned costs | Weight | Actual POC | Earned value |
|---|---|---|---|---|
| Foundation | 300,000 | 30% | 90% | 270,000 |
| Structure | 500,000 | 50% | 36% | 180,000 |
| Finishing | 200,000 | 20% | 0% | 0 |
| Project | 1,000,000 | 100% | 45% | 450,000 |
According to the plan, 50% should have been completed, and the actual costs are 480,000:
SV = 450,000 − 500,000 = −50,000: the project is behind schedule. Its progress is 5 percentage points below the plan.
CV = 450,000 − 480,000 = −30,000: the work performed has cost more than planned.
CPI = 450,000 / 480,000 = 0.94: each unit of cost has produced 0.94 of earned value.
The progress of 45% does not mean that the project is 5% late in time. It compares the value of the work done with the value of the work planned.
Aggregated and non-aggregated values
SAP calculates the progress of each object, and can also aggregate it up the hierarchy with weights. The project cost plan is the recommended weighting factor, as in the example above. An aggregated POC on the billing element can be used by results analysis, see period-end closing.
Tips
Set a maximum POC for estimates: 80% is a common value. It avoids tasks that stay "90% done" for months.
Choose simple techniques that people will really keep up to date.
Update confirmations, dates and milestones before you run the calculation.
Do not mix very different techniques within one WBS level if you want to compare the objects.